Whole house renovation tips: the order that keeps it on track

Renovating the whole house is many projects at once. The order you do them in matters more than any single finish.

  • Free to post
  • Only verified pros bid
  • No obligation
Related requests

How it works

  1. 1
    Post your job free

    Tell us what needs doing. Add photos and a budget if you like.

  2. 2
    Verified pros bid

    Only pros we approve can send you a price.

  3. 3
    Compare and hire

    Message pros, compare bids and pick the one you like.

A whole house renovation is a dozen projects sharing one schedule. Most of the stress comes from doing them in the wrong order: new floors scratched by the next trade, fresh paint opened up for wiring, a beautiful kitchen waiting on a back-ordered faucet. Here is the order pros follow, and how to keep the job moving.

1. What's behind the walls comes first

Start with the parts that protect the house and the systems that run through it:

  • Roof, gutters and anything that keeps water out
  • Foundation, framing and any structural changes
  • Windows and exterior doors
  • Plumbing, electrical, heating and cooling inside the walls

Then the inspections, then the walls close. Anything pretty comes after.

Tip: Photograph every wall before it is closed. Those photos show where pipes and wires run for as long as you own the house.

2. Top to bottom, outside in

Water and dust fall down. Finishing the outside first keeps weather out of new work, and working from the top floor down keeps finished rooms clean. Floors go in late, after the messy trades are done.

PhaseTypical work
OutsideRoof, windows, siding, drainage
Structure and systemsFraming, plumbing, electrical, HVAC, insulation
Walls and ceilingsDrywall, texture, primer
RoomsKitchen and bath cabinets, tile, counters
FinishesFlooring, trim, paint, fixtures, appliances

3. One person runs the schedule

Many trades in one house need someone who books them in the right order, gets inspections done and answers their questions the same day. That is the job of a general contractor or a project manager. Ask each candidate:

  • How will you phase the work, and which rooms stay usable?
  • Who pulls the permits and books the inspections?
  • How often will I get updates, and in what form?
  • How are changes and extra work approved?

4. Decisions come fast

A big renovation asks you to choose hundreds of things: tile, fixtures, flooring, paint colors, hardware. Choose and order as much as you can before work starts. Late decisions move pipes and outlets, and a single back-ordered item can stop the whole job.

What to expect

Expect dust, noise and some days where it looks like nothing is happening while inspections and deliveries line up. Expect at least one surprise behind a wall in an older house. A clear schedule, weekly updates and an agreed way to approve changes keep it calm.

Get whole house renovation bids on BidHandyman

Post your renovation once with photos and your plans, and local pros send you bids. Only pros approved by BidHandyman can bid. Compare their phasing and schedules side by side, message the pros and hire the one you trust, with no obligation. Request renovation bids, or read whole house remodel and hiring a renovation project manager.

Questions

Is it free to post a job?

Yes. Posting a job on BidHandyman is free for homeowners, and there is no obligation to hire anyone.

Who can bid on my job?

Only pros approved by BidHandyman can send bids. Each pro has a profile you can check before you hire.

How do I choose a pro?

Compare the bids side by side, message the pros with any questions, and hire the one you like.

What order should a whole house renovation follow?

Fix what is behind the walls first (roof, foundation, plumbing, electrical, heating and cooling), work top to bottom and outside in, close the walls after inspections, then finishes like floors, cabinets, paint and fixtures last.

What comes first in a whole house renovation?

The structure and systems: roof, foundation, windows and anything behind the walls, such as plumbing, wiring and ductwork. Finishes go last so they are not damaged or torn out.

Why top to bottom and outside in?

Water and dust fall down. Finishing the roof and outside first keeps weather out, and working from upper floors down keeps finished rooms clean.

Who should manage a whole house renovation?

One person should run the schedule: a general contractor or a project manager. They line up the trades in order, book inspections and keep decisions moving.

When should I choose finishes?

Before work starts, if you can. Tile, fixtures, flooring and paint colors decide where pipes and outlets go, and late choices or back-ordered items can stop the job.

Can I live in the house during a whole house renovation?

Sometimes, if the work is phased and one area stays livable. Many families move out for the dustiest parts. Ask each contractor how they would phase it.